In Webster County Missouri, the proposed interchange project is located near mile marker 103 on I-44, along the northern city limits of Marshfield, and approximately 2.10 miles northeast of the existing interchange of I-44 and Route 38 (Spur Drive).  The project is also within the limits of the Southwest Missouri Council of Governments (SMCOG), the regional planning commission for the area.  The project as presented, would provide connectivity from the I-44 North Outer Road (Western Termini) to MO-CC (Eastern Termini) – also known as old Route 66.  The proposed project is just north of the existing BNSF Mainline Track and the National Route 76 Transamerica Bike Trail that runs along Route 38. 

The Purpose and Need for this interchange include:  increasing roadway connectivity, reducing roadway congestion, enhancing roadway safety, encouraging economic accommodation, reducing emergency response times and finding a solution to these needs that is consistent with local and regional planning.  The “Base Project” includes the implementation of a new interchange with I-44 (Western Termini) that connects to MO-CC (Eastern Termini).  The ultimate build scenario would also include the future extension of MO-CC (From I-44 to MO-W), providing connectivity between MO-W, I-44, and MO-CC. 

There is not sufficient funding for the ultimate build scenario, so a phased approach has been developed to implement the “Base Project” from I-44 to MO-CC, that includes an added alternate for the extension of Elm Street from the new outdoor activity center to the new MO-CC if funding becomes available.

 

 

 
 

Status

 
Timeline

Passed Ballot Proposition

08/02/2016

Passed Ballot Proposition Authorizing the Issuance of $10,000,000 in General Obligation Bonds for the Interchange Project.

Approval

12/01/2016

Interchange Location Study Approval

Executed Agreement

04/13/2017

Executed Agreement for PH 1 Engineering Services with CMT

Application Submittal

06/29/2017

Cost Share Application Submittal

Preliminary Generation & Destination Report Submittal

08/16/2017

08/16/2017 – Preliminary Trip Generation & Destination Report Submittal

Final Trip Generation & Destination Report Submittal

09/26/2017

09/26/2017 – Final Trip Generation & Destination Report Submittal

Final AJR Submittal

11/28/2017

11/28/2017 – Final AJR (Access Justification Report) Submittal

Preliminary NEPA CE2 Document

12/15/2017

Preliminary NEPA CE2 Document

Executed Agreement for PH 2 Engineering Services with CMT

12/21/2017

12/21/2017 - Executed Agreement for PH 2 Engineering Services with CMT

Executed Cost Share Agreement

01/11/2018

Executed Cost Share Agreement Between City & MoDOT

Final NEPA CE2 Document

02/08/2018

02/08/2018 – Final NEPA CE2 Document

Preliminary Plans Due

02/23/2018

Preliminary Plans Due

Preliminary Plan Approval

03/12/2018

03/12/2018 - Preliminary Plan Approval

Design Hearing

04/03/2018

Design Hearing

ROW Plan Submittal to MoDOT

05/01/2018

05/01/2018 – ROW Plan Submittal to MoDOT

Design Hearing Approval

05/02/2018

Commission Design Hearing Approval

ROW Plan Approval

05/15/2018

ROW Plan Approval

Final Plan Submittal

01/18/2019

Final Plan Submittal to MoDOT

Advertisement Date

04/11/2019

Advertisement Date

Letting Date

05/17/2019

Letting Date

Construction Complete

12/31/2020